Cauvery project Stage V

In News
  • Bangalore Water Supply and Sewerage Board (BWSSB) chairman Ram Prashanth Manohar sought the support of all MLAs and MPs representing Bengaluru for revising drinking water tariffs amid rising operational costs and financial shortfalls.
Cauvery Water project
  • The fifth phase of the 50-year-old project was commissioned on October 16, 2024, to supply drinking water to new extensions of Bengaluru – 110 villages, spread over 225 sq km, that were added to the city in 2007.
  • Water from the perennial Cauvery river is filtered and transported through pipelines over a distance of 86 km to Bengaluru.
  • Since the city is at an elevation of 900 m (3,000 ft) above sea level, much higher than the river, five pumping stations pump the water to a height of almost 450 metres (1,500 feet).
  • Within the city, the water is distributed through a network of almost 8,000 km of pipelines.
  • The BWSSB has to bear the cost of pumping the water, as well as service the loans taken to build the supply system.
History of project
  • Till the end of the 19th century, Bengaluru’s drinking water needs were served by a network of lakes and tanks in the city, and local wells and ponds.
  • As the city began growing in the 20th century, the Arkavathi river, which flowed along the western edge of the city, became a source for the supply of water to the city.
  • By the 1960s, however, as the population of Bengaluru hit the 16-lakh mark, the 185 million litres per day that the Arkavathi supplied began to prove inadequate. It was then that the Cauvery was identified as a new source of water for the growing city.
  • Stage I of the Cauvery Water Supply Scheme (CWSS) was commissioned in 1974 to add 135 million litres per day (MLD) of water supply to Bengaluru.
  • CWSS Stage II followed in 1982, augmenting supply by another 135 MLD. Stage III and the first phase of Stage IV of the CWSS were commissioned in 1994-95 and 2002 respectively to add 270 MLD in each phase.
  • Phase II of Stage IV was commissioned in 2012, adding a further 500 MLD to the supply.
  • At the end of Stage IV, the Cauvery project had an installed capacity for the supply of 1310 MLD at the water treatment stage (and 1,460 MLD at source) to Bengaluru.
  • This water was being supplied to the core areas of the city, including seven former city municipal councils and one town municipal council, covering a total area of 575 sq km.
  • Over the last 50 years of the CWSS, however, the population of Bengaluru has grown massively from about 16 lakh to 1.5 crore.
  • In 2014, the state government decided to implement Stage V of the scheme to provide an additional 775 MLD of Cauvery water to new extensions to the city, including the 110 villages added in 2007. Stage V adds 500 MLD and 275 MLD of installed supply capacity in two phases.
Cost of the project
  • The project is funded by a mix of state government resources and loans from the Japan International Cooperation Agency (JICA).
  • Stage V involved an investment of Rs 4,300 crore, of which JICA contributed Rs 3,000 crore. A sixth phase is planned as well, at an estimated cost of Rs 5,200 crore.
  • Since Stage III, JICA has provided loans of more than Rs 9,500 crore for the project: Rs 1,897 crore in 1996, Rs 2,800 crore in 2005, Rs 1,891 crore in 2006, and Rs 3,000 crore in 2018.
Source- Indian Express

More Related Current Affairs View All

20 Dec

National Quantum Mission

'National Quantum mission be implemented by the Department of Science & Technology (DST) under the Ministry of Science & Technology.' The mission planned for 2023-2031 a

Read More

20 Dec

First-ever satellite tagging of a Ganges dolphin

'The first ever Ganges river dolphin (Platanista gangetica) was tagged in Assam is being deemed as a historic milestone for Project Dolphin, the movement aimed towards conserving I

Read More

19 Dec

Parliamentary Standing Committee recommendations on MSP

'A parliamentary committee  has recommended implementing a legal guarantee on Minimum Support Price, amid a slew of measures to improve farmers’ welfare.' The Parli

Read More

India’s First Ai-Driven Magazine Generator

Generate Your Custom Current Affairs Magazine using our AI in just 3 steps